Six machines, each working at the same constant rate, together can complete a job in 12 days

Solved 1 Answers 10379 Views
GMAT Timer00:00

Six machines, each working at the same constant rate, together can complete a job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?
A. 2
B. 3
C. 4
D. 6
E. 8

Official Answer

1 Best Answer

Jsy Singh
1
Best answer
The questions asks us to calulate the how many additional machines are required to the complete the same quantam of work from 12 days to 8 days.
Let us calculate total work done by 6 machines in 12 days => 6  x 12 = 72 units.
Now, We need to complete this work in 8 days => 8 x ( no of machines )
Since the quantam of work to be completed has to be same so,
72 units = 8  x a
on solving we get a => 9.
Now be careful, we need answer the additional machines. which would be 9 - 6 = 3
hence the answer is B
answered Mar 25, 2015 by Senior Associate (437 points)
selected Mar 26, 2015 by
Student Speaks

Jyotsna Mehta

Indian School of Business, Co'18

I am very thankful to Gmatxchange and would definitely recommend Gmatxchange mentors to all those students applying for MBA admissions

Your Tentative GMAT Score
Estimate your GMAT score.
700
The scorer helps you to determine your current level within a few questions you solve.Read More
Please log in or register to use the Scoring Feature
Confused about your profile & colleges, Get FREE profile evaluation today from over 10 consultants.
Follow us and get quick prep updates on Facebook
...